The construction of a new overbridge on the Coventry Road, that will allow high-speed trains to travel across four tracks under the A45, has reached the pivotal halfway mark.
Over the past eleven months, a team of engineers working for HS2’s construction partner Balfour Beatty VINCI (BBV), have successfully completed the first section of the new Coventry Road overbridge, near Bickenhill. This unique structure is being constructed in two halves, to ensure that existing traffic flows along the A45 are maintained, minimising impacts on the local road network.
Using the ‘top down’ construction method, approximately 7,5000 tonnes of earth was excavated from beneath the existing carriageway. The team then installed 46 piles, at depths of up to 23 metres, and built the pile caps to support the weight of the new 2,000-tonne bridge deck.
Over the summer months, 13 pre-stressed pre-cast concrete beams were lowered into place to support the 37-metre span bridge deck, and 13 parapet units were successfully installed to one half of the structure.
Completion of the waterproofing and highway works in the coming weeks means the eastbound section of the new structure will soon be brought into use, and HS2 is working closely with National Highways to prepare for the upcoming traffic management changes.
From Monday, 7th December, a series of overnight and weekend closures will be put in place to facilitate the traffic switchover. Once complete, motorists will begin using the temporary carriageway alignment over the new eastbound section of the bridge.
Paul Marshall, Head of Delivery at HS2 Ltd said:
“Our engineers have worked incredibly hard to develop a design solution that maintains traffic flows in each direction, while we build the bridge and excavate the ground below to make way for the new high-speed railway.
“During the temporary weekend and night-time closures, to facilitate the traffic switchover onto the new bridge, we’ll ensure that access to businesses and properties is maintained.
“I’d encourage motorists to familiarise themselves with the diversion routes and thank them for their patience.”
In the new year, BBV’s engineering team will start work on the second section of the bridge, following a similar sequence of works.
Below the structure, hidden from view, the team will continue excavating the trace – which will ultimately carry four railway tracks towards the new Interchange Station, just one mile away. The tracks will serve the station’s four platforms, which are made up of two 425-metre-long platform islands.
Richard Husbands, Balfour Beatty VINCI’s Project Manager said:
“The Coventry Road overbridge is one of the key crossings on this part of the route, allowing the railway to pass under the A45 as it approaches Interchange Station. Construction of the bridge in two halves is a complex engineering challenge, and reaching the halfway stage is an important milestone for the project.
“The programme we’re working to has been designed to minimise disruption for motorists and local communities as much as possible. We’re grateful for everyone’s continued patience, as we move to the next phase of construction.”
Above ground, construction will continue throughout 2027. The bridge is expected be structurally complete by the end of the year.
In liaison with National Highways, engineers will then carry out the permanent highway works, installing lighting, kerbs, drainage, and permanent carriageway, with the final structure and road alignment expected to be in use by summer 2028.