HS2 tunnel boring machines reach halfway on journey to Euston: HS2 Euston tunnel halfway bored
HS2 tunnel boring machines reach halfway on journey to Euston: HS2 Euston tunnel halfway bored

HS2 tunnel boring machines reach halfway on journey to Euston

  • 2.25miles of HS2’s fifth and final deep tunnel bored since January and March TBM launch
  • More images of Euston Tunnel and Euston TBMs here

Building work on HS2’s Euston tunnel passed the halfway mark this week as two giant tunnel boring machines (TBMs) edged their way towards the high-speed railway’s ultimate London terminus.

Delivering the railway to a new HS2 station at Euston will enable the high-speed line to carry fast intercity services that previously used the West Coast Mainline. The capacity released on the southern section of the existing route will unlock opportunities for new services for towns and cities between London and Birmingham, as well as boosting the economic potential around intermediate stations. 

Launched in January and March 2026 from HS2’s future super hub at Old Oak Common, the two 1,624-tonne TBMs – Karen and Madeleine – have since been working towards Euston at a rate of 16 metres per day. By 17 November both were in the area between West Hamstead and Kilburn High Road stations. 

Operated by Skanska Costain STRABAG joint venture (SCS JV) - HS2 Ltd’s London tunnels contractor– both machines work 24/7 to tunnel the 4.5miles into central London.

The programme is expected to generate 1.5million tonnes of excavated material. As well as tunnelling, the TBMs will line the tunnel with 48,294 concrete ring segments which are being made in Hartlepool in the North East of England.

The Rail Minister Lord Hendy said: 

“This achievement marks another important step in delivering HS2 into the heart of London.

 “The progress made by the tunnelling teams shows the momentum being built on the project as we work to deliver a railway that provides greater capacity, faster journeys and long-term benefits for growth, jobs and homes."

HS2 Ltd chief executive Mark Wild said:

“Reaching the halfway mark for building the programme’s last deep bored tunnel is a magnificent achievement by everyone involved. Their work driving the high speed line into central London is fundamental to the long term ambition of increasing the prosperity of the area around Euston. I wish everyone a safe journey to their final destination.

“HS2 Ltd is now in the last phases of a root and branch full-programme reset that will safely deliver the railway at lowest reasonable cost.  The new line we’re driving to Euston will complement the existing station and the West Coast Mainline, providing fast and reliable long distance journeys with its new capacity.”

Skanska Costain STRABAG Delivery Lead, Eddie Edmonds said:

“It’s a fantastic technical achievement to be 50% of the way through construction of HS2’s final running tunnels. Months of meticulous planning and preparation have brought us to this point and into the final leg of the journey. This progress is down to that preparation and the skill, expertise and diligence of the teams working not only on the tunnel boring machines, but also those supporting the operation and carrying out the many other tasks essential to its success. The fact that this complex operation is taking place up to 50 metres beneath London makes it an even greater achievement.”

The TBMs will complete their journeys in 2027, finishing underground on the approach to Euston. Once stopped, key elements of the machine will be pulled back through the tunnel. The cutterhead, spanning 8.53-metres will be excavated from the Euston Cavern and removed. The outer part of the front of the machine, known as the shield or ‘can’, will remain underground and will be grouted in behind the concrete tunnel lining.

The area around the station at Euston is one of London’s biggest development opportunities. Harnessing its potential will be led by a new Euston Delivery Company, which will lead delivery of an affordable and integrated transport hub - including the new HS2 station, the redevelopment of the existing station, and upgrades to the London Underground station - along with commercial development across the Euston campus.